Inspection Process

Once your application has been formally accepted you may commence works after 48 hours.

Note : Until a formal decision has been made on a "Full Plans" application, any works that are carried out will be at your own risk and inspections will be made without prejudice.

Notification for site inspections will be accepted either verbally, letter or e-mail. A same day service will be provided for inspection requests received before 10:00 am. Telephone 01302 734848 or e-mail building.control@doncaster.gov.uk

You are obliged to notify Building Control when you have reached the following stages of works:-

 Additional inspections may be required either by request of the Building Control Officer or by the applicant/builder.

Party Wall etc. Act 1996

The Party Wall etc. Act 1996 provides a framework for preventing disputes which may arise between neighbouring owners, in relation to the construction and repair of party walls, boundary walls and excavations near neighbouring buildings. If you intend to carry out work which involves:

you must give the adjoining owners notice of your intentions in a way that is set down in the Act. Adjoining owners can agree or disagree with what is proposed. Where there is a disagreement the Act provides for the resolution of disputes.

You may need to employ your own private surveyor to fulfill the duties as this is not enforceable by building control.

Please click on the link below for further information :

Last Updated - Friday, 05 September 2008
Doncaster Council,
Council House, College Road,
Doncaster, DN1 1BR
Tel: +44 (0)1302 736000
eMail: General Enquiries