BSF - the year at a glance

eMail: BSF.Team@doncaster.gov.uk | Telephone:  01302 736033 
Address: BSF Team, The Blue Building, 38-40 High Street, Doncaster, DN1 1DE.

June 2008 - May 2009

June - August 2008

One-to-one meetings with the Mayor and each secondary school Headteacher and Chair of Governors

Ongoing consultation including establishing the BSF Stakeholder Forum and School Stakeholder Groups

Prepare the Strategy for Change Part 1 (SfC)
September 2008

Submit the SfC1 to the Department for Children, Schools and Families (DCSF)

September 2008 - January 2009

Prepare the Strategy for Change Part 2 (SfC2) – this provides more detail and outlines our plans to deliver the project.

Ongoing consultation about the development of the SfC2

January 2009Submit the SfC2 to the Department for Children, Schools and Families (DCSF)
January - April 2009Prepare the Outline Business Case (OBC) which contains indepth detail about how the project will progress. It will include things like the cost, risks and a clear timetable of activities. This document will determine how much
funding Doncaster will have for the BSF programme.
May 2009Submit the OBC to the Department for Children, Schools and Families (DCSF). Feedback should be provided by
August 2009.
Last Updated - Friday, 06 June 2008
Do you want to receive an update when this page is updated?