| June - August 2008 | One-to-one meetings with the Mayor and each secondary school Headteacher and Chair of Governors Ongoing consultation including establishing the BSF Stakeholder Forum and School Stakeholder Groups Prepare the Strategy for Change Part 1 (SfC) |
| September 2008 | Submit the SfC1 to the Department for Children, Schools and Families (DCSF) |
| September 2008 - January 2009 | Prepare the Strategy for Change Part 2 (SfC2) – this provides more detail and outlines our plans to deliver the project. Ongoing consultation about the development of the SfC2 |
| January 2009 | Submit the SfC2 to the Department for Children, Schools and Families (DCSF) |
| January - April 2009 | Prepare the Outline Business Case (OBC) which contains indepth detail about how the project will progress. It will include things like the cost, risks and a clear timetable of activities. This document will determine how much
funding Doncaster will have for the BSF programme. |
| May 2009 | Submit the OBC to the Department for Children, Schools and Families (DCSF). Feedback should be provided by
August 2009. |